Daewoo E&C Completes $440M Al-Faw Port Highway Project in Iraq on July 8

According to Yonhapinfomax, on July 8, Daewoo E&C completed construction of a highway connecting Iraq's Al-Faw port and Umm Qasr. The company received completion approval from Iraq's port authority at the end of June.

The $440 million design-build project ran from August 2021 to May 2025, followed by a one-year defect liability period. The roadway features four lanes, two bridges, and three roundabouts, with advanced pavement design systems engineered to handle heavy cargo vehicles.

Disclaimer: The information on this page may come from third-party sources and is for reference only. It does not represent the views or opinions of Gate and does not constitute any financial, investment, or legal advice. Virtual asset trading involves high risk. Please do not rely solely on the information on this page when making decisions. For details, see the Disclaimer.