Lundin Mining's Caserones Copper Mine to Resume in 2-3 Weeks After July 18 Blackout

According to Lundin Mining, on July 18, the Caserones copper mine in Chile was disconnected from power after a severe storm damaged two transmission towers supplying the facility. The company announced on Monday that heavy rainfall and snowfall caused the infrastructure damage.

Lundin Mining expects operations to resume within approximately two to three weeks. The company's teams are working to repair the damaged transmission infrastructure, and road access to the mine is gradually being restored.

Disclaimer: The information on this page may come from third-party sources and is for reference only. It does not represent the views or opinions of Gate and does not constitute any financial, investment, or legal advice. Virtual asset trading involves high risk. Please do not rely solely on the information on this page when making decisions. For details, see the Disclaimer.